​Coastal GasLink set to lay first pipe as it ramps up LNG pipeline construction

Image: Coastal GasLink

Coastal GasLink says it is ready to launch its summer construction program in British Columbia, which will see the first section of pipe buried in the ground next month.

The company says in a statement that construction also begins this summer on a compressor and metering stations that will form anchor points along the 670-kilometre pipeline running from the Dawson Creek area to Kitimat.

Work on the main compressor station is slated to begin in July and the company says activity on the entire project will gradually ramp up in the following months.

It expects to reach a peak in September, with a workforce of more than 2,500.

Opposition by the hereditary chiefs of the Wet'suwet'en Nation to construction of the pipeline through their traditional territory set off demonstrations and blockades that shut down large parts of the national economy in February.

When complete, Coastal GasLink says its pipeline will deliver at least 2.1-billion cubic feet of natural gas everyday to a LNG Canada liquefied natural gas facility being built in Kitimat.

Contempt of court charges were dropped this month against 22 members of the Wet'suwet'en and their supporters who were arrested in northwestern B.C. during protests against the pipeline.

© 2020 The Canadian Press

Dear user, please be aware that we use cookies to help users navigate our website content and to help us understand how we can improve the user experience. If you have ideas for how we can improve our services, we’d love to hear from you. Click here to email us. By continuing to browse you agree to our use of cookies. Please see our Privacy & Cookie Usage Policy to learn more.