​How Suncor’s new oilsands mine signals a path for investment revival

Suncor Energy CEO Steve Williams speaks at the opening of the Fort Hills oilsands mine on Monday, Sept. 10. Image: Joey Podlubny/JWN

A massive Canadian oilsands project may be showing the way forward for an industry some thought would never see major new investments.

In a forest clearing roughly the size of Cleveland, building-sized trucks dump tons of oily soil into a massive crushing facility, while conveyors move the dirt on the other end to a plant where hot water and solvents will turn it into heavy crude for U.S. refineries.

Welcome to Fort Hills, a Suncor Energy Inc. oilsands mine in northern Alberta that had its formal opening on Monday.

The sprawling complex in Canada’s freezing wilderness was thought to mark the end of an era for big projects of its kind, but its lower carbon emissions, combined with lower costs, may offer a blueprint for new mines, say analysts including Wood Mackenzie Ltd.’s Mark Oberstoetter.

A return of investments to the oilsands, even if timid, would follow similar moves offshore. In April, Royal Dutch Shell Plc. decided to proceed with its 100,000 bbl/d Vito project in the Gulf of Mexico.

“We are starting to see a return to the big projects,” said Oberstoetter, lead analyst for Canadian upstream research at the firm.

The collapse of oil prices from more than $100-a-barrel in mid-2014, to less than $30 in early 2016, triggered an exodus of major multinationals from the region and forced Canadian producers to cut costs dramatically.

Now, new technologies such as driverless trucks and froth-treatment that eliminates the need for multibillion-dollar upgraders -- along with U.S. benchmark crude prices closer to $70 now -- are helping make the industry profitable again.

Suncor announced last week that driverless haulers are now in commercial service at its North Steepbank oilsands mine. The company is currently considering the implementation plan for the technology at Fort Hills -- all of the haulers in use at the project are capable of running autonomous.

While the upfront spending on an oilsands mine tends to be costlier than developing more common drilled thermal projects, their large scale and decades-long lifespans can make them lucrative in the future for companies willing to wait, said Kevin Birn, a director on the North American crude oil markets team at IHS Markit.

“The trick is getting over that upfront cost,” Birn said. “It depends on how you view that future cash flow. If you are willing to be patient, the attractiveness of that mine is more.”

Suncor expects Fort Hills will produce as much as 194,000 bbls/d when it reaches maximum speed before the end of the year. That’s more than the output from OPEC member Gabon.

While the Calgary-based company doesn’t plan to invest in a new mine for at least the next decade, after spending more than C$17 billion ($13 billion) on the project, Vancouver-based Teck Resources Ltd. continues to advance another greenfield project.

A Fort Hills joint venture partner, Teck is pushing for approval of the C$20 billion, 260,000-bbl/d Frontier mine project that goes before a regulatory hearing panel later this month. The mine could be pumping out crude by 2026 and stay in operation for another 41 years should Teck receive the go-ahead and decide to build it.

Frontier would be built near the Wood Buffalo National Park, making it the farthest north of any oilsands mine. The project faces opposition from some indigenous groups in the area who are concerned the site will harm land that they use and resources including a local bison herd.

Frontier would use centrifuges to reduce the volumes of liquid in tailing ponds, requiring less overall water, said Chris Stannell, a company spokesman. The company has developed a “comprehensive mitigation, monitoring and adaptive management plan for wildlife, including bison” in consultation with indigenous communities, he said. Greenhouse gas emissions intensity would be about half the oilsands industry average, according to the company.

Meanwhile, Suncor’s new Fort Hills mine is operating better than planned, producing 150,000 bbls/d, and will ramp up to full capacity in the fourth quarter, Suncor Chief Executive Officer Steve Williams said at the site Monday.